Solution Step 1: Wear anti-static gloves before handling the LED Modules. Step 2: Remove the Vacuum Suction Tool from the box and press its power switch to use it. Please charge it with the included power supply and make sure the vacuum suction tool is kept in a fully charged state. Step 3: Move the Vacuum Suction Tool to t...
DVLED Display with an entire column of unlit LED Modules. Answer: There may be poor connection or loose wiring with the connectors from the System Control Box to the LED Module adapter board. Solution The column's most bottom LED Module will need to be removed with the Vacuum Suction Tool in order to access the connectors. ...
When you find that the edge brightness of the LED module is different from that of the adjacent modules, the following procedure below can be followed in order to resolve the problem. Solution Step 1: Use the USB B-to-A cable and HDMI cable to connect the monitor to the computer, and switch the monitor's input source to HDMI. Step...
The Bracket installation order varies from the Floor Stand configuration. Please follow the steps in the respective order for the Wall-mount configuration: Appropriate location and center point found for installation (e.g. upper bracket mounted at least two meters above the ground for a 135" LED display; for other display sizes, check corresp...
Please refer to this link before beginning any Direct View LED Display installs. Solution Step 1: Install the Wall-mount brackets Step 2: Install the Cabinets onto the Floor Stand, connect the System Control Box to the Cabinets Step 3: Install the System Control Box onto the Floor Stand Step 4: Install the LED Modules onto t...
The Transfer Board (also known as a Transfer Card) is an internal component that facilitates signal connections between LED modules and the cabinet. Note: Current models have largely transitioned to "3-in-1 Boards." This article is for legacy product maintenance and technical reference only. Key Functions: Signal Supplementing: Routes ...
Answer: LED displays do not have a fixed power consumption and are rarely at maximum power consumption. Therefore, power consumption will vary. Maximum power consumption will be achieved for pixels emitting white light. Pictures with more white light will result in higher brightness, therefore, consuming more power. Higher overall bri...
The DVLED installation process has multiple steps and the guidelines are given to those who wish to receive training. Installation should be done by personnel who have received training. Please refer to the installation video for a brief installation demonstration. Please contact your regional office for DVLED training-related questions. ...
Answer: There may be damage to the LED module's circuitry. Please check for unlit LEDs and refer to the LED Acceptance Criteria to replace appropriately. Related link: "Do I have to wear the anti-static gloves when installing LED modules for the DVLED Display?"
The Dehumidification service (or Dehumidification process) can be used to protect the LED module(s) by displaying a dark screen and gradually transitioning to a lighter screen. The concept is to gradually remove humidity by slowly heating up the circuitry - since a lighter colored screen uses more power than a darker colored screen. The total p...